Project:
Sanderstead Road Bridge Replacement, between Broomhall Road and Purley Road
Location:
Sanderstead Road, Purley, South Croydon
Client:
Network Rail, on behalf of Bam Nuttall
Area Covered:
3,000m2
Solution:
SUREGROUND™ Reversible Soil Enhancement System
Network Rail required the removal of a road bridge in South Croydon on Sanderstead Road. The inner-city location meant that works would need to be completed with minimised construction traffic and to a short programme.
The scheme required Soil Science to both install and decommission the ground using the SUREGROUND™ Reversible Soil Enhancement System on behalf of the main contractor Bam Nuttall.
During construction, topsoil was stripped and bunded before the proprietary binder was rotovated with soils using a Stehr dust free mixer. This was surfaced with SUREGROUND™ Maintenance Free Surface Armouring saving further costs.
The enhanced area was then decommissioned by the introduction of a bespoke reagent, the composition of which was specific for the site soils. This restored pH and nutrients to within their pre-start DEFRA indices.
The area was stripped of stone surfacing and this was recycled. The reagent was then mixed with previously enhanced soils before topsoil was spread and turf was applied.
- COST SAVING 30%
- Maintenance Cost Saving 25%
- Programme Reduction 50%
- Vehicle Movements Reduction 79%
- Associated Carbon Emissions Reduction 59%
- Imported Aggregate Reduction 78%
- Material sent to landfill reduced by 100%
- Stone Layer Depth Reduction 80%
- COST SAVING 30%
- Maintenance Cost Saving 25%
- Programme Reduction 50%
- Vehicle Movements Reduction 79%
- Associated Carbon Emissions Reduction 59%
- Imported Aggregate Reduction 78%
- Material sent to landfill reduced by 100%
- Stone Layer Depth Reduction 80%
Get in touch
For further information about our services, please call us on 0118 3389 530 or
As used by















